Bid Date: 2026-01-30

Project Description:
See attached for Scope of Work.

Line item #!: Clearing woody vegetation for one acre.
Line item #2: Clearing woody vegetation for two acres.
Line item #3: Clearing woody vegetation for 3.5 acres.

Pre-bid meeting.
Wheeled and tracked machinery are only allowed on the road due to potential archaeological sites. No ground disturbance. Only handheld machinery, such as chainsaws, is allowed.

Amendment
01/27/2026
Update:
Machinery will only be allowed on the road. No machinery off the road for this project.

Plans

Specifications

Waianae Kai FR Vegetation Clearing for the Hawaiian Hardwood Project Scope of Work.docx
AG-008 103D General Conditions (1.10.23).pdf

Addendums/Amendments