Bid Date: 2025-12-14
Project Description: The Contractor shall provide all labor, tools, equipment, and materials to perform all work related to the removal of existing carpet and installation of Vinyl Composite Tile (VCT) in the main entrance room and (4) adjoining bedrooms. New cove base shall be installed in all rooms excluding the bathrooms. See details below regarding the requirements of this project. Additional information is provided on Attachment 2a.
Amendment
12/08/2025
Added a requirement “Apply (2) coats of floor wax” to the scope of work (SOW)
12/10/2025
Pre-Bid Conference date and time needed to be changed to reflect December 12, 2025 @ 8:00am