Bid Date: 2025-12-14

Project Description: The Contractor shall provide all labor, tools, equipment, and materials to perform all work related to the removal of existing carpet and installation of Vinyl Composite Tile (VCT) in the main entrance room and (4) adjoining bedrooms. New cove base shall be installed in all rooms excluding the bathrooms. See details below regarding the requirements of this project. Additional information is provided on Attachment 2a.

Amendment
12/08/2025
Added a requirement “Apply (2) coats of floor wax” to the scope of work (SOW)

12/10/2025
Pre-Bid Conference date and time needed to be changed to reflect December 12, 2025 @ 8:00am

Plans

Specifications

2a Photo Description YCA B1786 Rm 304 Carpet and Flooring.pdf
4 Special Provisions Const ACT 52 and 68 Rev.pdf
5 General Conditions Table of Contents.pdf
5a General Conditions.pdf
6 HIePRO Construction Offer Form.pdf
AG-008 103D General Conditions (1.10.23).pdf

Addendums/Amendments
1 SOW YCA B1786 Rm 304 Carpet and Flooring Ammendment 1.pdf