Bid Date: 2026-11-17

Project Description:
CPY 1 Width: 51’ 6” Height: 4’ 0” Projection: 13’ 6” approximate. Contractor is responsible to measure and template the frame to ensure exact fit and accurate bid. Fabric: Proof 502 70.87” or approved equivalent.

Special Instructions
* Contractor must be properly licensed with a State of Hawaii Specialty contractor license
* Contractors are to use OPM Form 54 to list any subcontractors to be used on this project, if applicable. See attachment
* Contractor must comply with the attached General Provisions for Construction Request for Quotations (RFQ)(Small Purchases). See attachment.
*Contractor must be fully insured/bonded according to University of Hawaii requirements. See the attached insurance requirements and bonding requirements in the general provisions.
*Contractor must comply with prevailing wages according to University of Hawaii requirements. See attachment.
* Hawaii Compliance Express clearance is required prior to Award and final payment.
* Vendor should not solely rely on provided plans or stated dimensions. Contractor is responsible to measure and template the frame to ensure exact fit and accurate bid.
* The front curved edges, called catenaries, and the grommet areas will be sewn using UV- inert thread.
* Warranty on this thread matches whatever warranty fabric it is sewn into.
* Request for a site visit upon arrival of materials on island for the canopy to establish a reliable fabrication window, installation date and to coordinate removal of the existing fabric and a time frame to complete the rust remediation and painting of existing frame around that schedule.

Specifications:
* design, manufacture, and installation of one (1) replacement canopy fabric cover for the existing frame
* include all fabric, roping, stainless steel cabling, and hardware required for the recover.
* main fabric deck shall be manufactured using welded seams (where the fabric meets on the rafters)
* front catenaries shall be sewn using Tenara thread.
* Fabrication and installation shall be performed under the management of an internationally recognized Master Fabric Craftsman (MFC).

Addendum
11/13/26
Closing date extended to Tuesday Nov 17, 2026:
Contractor is responsible to measure and template the frame to ensure exact fit and accurate bid.

Plans

Specifications

SQ120835. GenProv Construction-RFQ (EFF. 09-13).pdf
SQ120835. Insurance rev 11-1-2020 OGC 092820.pdf
SQ120835. Sub contractor form. OPM-Form-54.pdf
SQ120835. Wages Hours. eH104-3-rev-05-24.pdf

Addendums/Amendments