Bid Date: 2026-08-07

Project Description:
Provide all tools, materials, equipment, and insurance necessary to remove and replace approximately 200-feet of 8-inch storm drain pipe. The existing concrete storm drain pipe is blocked with tree roots and soil, and needs to be properly re- sloped to ensure adequate drainage. Install new C900 PVC pipe and fittings, pipe cushion material, and test & dispose of any excess fill and waste materials. All plumbing, mechanical, and soil work shall be in accordance with local and national codes.
Labor; hours x labor rate.

Special Instructions
A site visit is scheduled for Tuesday, August 4th @ 9:00 am. All interested parties shall meet at the Multipurpose Building, 1776 University Avenue.

Plans

Specifications

University of Hawaii, Request For Quotation #116701.pdf

Addendums/Amendments
University of Hawaii, Request For Quotation #116701, Addendum #1.pdf