Bid Date: 2026-05-18
Project Description:
Provide all labor necessary to replace the condenser coil as indicated in the plans
and specifications. The proposed work shall generally include removal, disposal and
replacement of the condenser coil and drier, sight glass per manufacturer’s
specifications; any insulation that is removed must be replaced with new. Start-up
the unit per manufacturer’s recommendations and perform system checks to confirm
proper operations. Submit all data collected to the university of Hawaii facilities
management office, attention: Carl Oshiro prior to request for final inspection. All
work located at C-More, UHM.
Provide all tools, materials, equipment and insurance necessary to replace the
condenser coil as indicated in the plans and specifications. The proposed work shall
generally include removal, disposal and replacement of the condenser coil and drier,
sight glass per manufacturer’s specifications; any insulation that is removed must be
replaced with new. Start-up the unit per manufacturer’s recommendations and perform
system checks to confirm proper operations. Submit all data collected to the
university of Hawaii facilities management office, attention: Carl Oshiro prior to
request for final inspection. All work located at C-More, UHM.
Special Instructions
ALL bidders are requested to attend a mandatory site walk-through. A site walk through is
scheduled for 8:00pm. on Monday May 11, 2026. Contractors shall meet at the
Physical Plant Mechanical Engineer Office located at 2002 East- West Road. Contract
documents will be distributed at the mandatory walk through. Contractors interested in
bidding this work must contact Carl Oshiro through email ( coshiro6@hawaii.edu), facsimile
(956-5979) or phone (956-0479) to confirm attendance by 4:00 p.m. Friday May 8, 2026.
Contractors who DO NOT attend a mandatory site walk-through will not be allowed to bid on
this work. Contractor is required to provide a cost breakdown at time of bid. The
breakdown must equal to the total cost of the bid. If correct breakdown is not provided at
time of bid, the bid may be disqualified.
No attachments have been added to this solicitation.
Addendum
05/11/26
Additional work for the feezer walk-in. remoave and replace the compressor, liquid ejector and the compressor contactor.