Bid Date: 2026-01-21

Project Description: Clearing and mulching Requirements: Clear the entire one-acre area using equipment suited for the terrain. Fell, remove, and dispose of all non-protected standing trees, brush, shrubs, grasses, and undergrowth that cannot be chipped or mulched. Backfilling: Fill all depressions created so the ground surface is a consistent, level grade suitable for routine maintenance and safe operation of mowing equipment. Debris Handling: Collect, remove, and dispose of all green waste, stumps, logs, and debris from the site that cannot be chipped or mulched.

All disposal or burning must comply with local, state, and federal regulations, including Hawai’i County open burning rules.


Notes
Proposal Validity: Submit a detailed quote for the Scope of Work described above. The quote must include the cost of mulching felled trees on-site and remain valid for a minimum period of 90 days from the submission date.

Certificate of Tax Compliance: Provide a current Certificate of Tax Compliance demonstrating good standing with state and federal tax obligations.

Certificate of Insurance: Submit a valid Certificate of Insurance naming the Department of Hawaiian Home Lands (DHHL) Association Lease/License holders as additional insured.

Additional Documentation: Be prepared to provide any additional insurance documentation or certifications required by the Research Corporation of the University of Hawai’i (RCUH) as part of the contracting process.
Special Instructions
Location: TMK: (3) 2-2-047: 075 - Pana’ewa (Hilo), Hawai\'i Island, see attached maps.

The Contractor shall provide all necessary labor, materials, equipment, and related services required to complete the clearing and mulching of one (1) acre of land, in preparation for a native agroforestry project. All work shall be performed in accordance with the specifications outlined below and in compliance with all applicable local, state, and federal regulations.

1. Work Area and Site Preparation
Visiting the site to view the particular section to be cleared is highly recommended. The POC for this RFB can be contacted to arrange a viewing. The designated one-acre area will be clearly identified in a walk through and flagging with the land manager and University of Hawai’i representative. The Contractor is responsible for clearing all standing vegetation within this area, including the felling and removal of all trees.

2. Clearing and Mulching Requirements
All standing trees must be felled, chipped, or mulched on-site, wherever possible. Any remaining debris, including brush, stumps, and tree materials that cannot be chipped, must be completely removed and properly disposed of off-site. All stumps and root systems must be leveled so that a riding mower can maintain the area post-clearing.

3. Site Condition Upon Completion
The cleared acre must be left in a mowable condition.

Any large holes or depressions resulting from stump/root removal must be backfilled and leveled to create an even surface suitable for future maintenance.

4. Environmental and Regulatory Compliance
All clearing and disposal work must comply with regulations concerning open burning and environmental protection.

No burning shall be conducted without express written approval and permits, if applicable.

5. Community and Stakeholder Engagement
The Contractor must have prior experience working with Native Hawaiian community members and Department of Hawaiian Home Lands (DHHL) leaseholders.

The Contractor is expected to communicate regularly and effectively with the RCUH/University of Hawai’i representative and designated land managers to ensure alignment with project goals.

6. Coordination and Approvals
The Contractor must obtain prior written approval for any work that deviates from this Scope or is not explicitly included in the service agreement.

All coordination with the Buyer and land manager must be documented, and no additional work shall be performed without formal consent.

7. Other Requirements
All bidders must meet the following requirements to be considered for this project:

Proposal Validity:
Submit a detailed quote for the Scope of Work described above. The quote must include the cost of mulching felled trees on-site and remain valid for a minimum period of 90 days from the submission date.

Certificate of Tax Compliance:
Provide a current Certificate of Tax Compliance demonstrating good standing with state and federal tax obligations.

Certificate of Insurance:
Submit a valid Certificate of Insurance naming the Department of Hawaiian Home Lands (DHHL) Association Lease/License holders as additional insured.

Additional Documentation:
Be prepared to provide any additional insurance documentation or certifications required by the Research Corporation of the University of HawaiE>>i (RCUH) as part of the contracting process.

Time Frame
Start Date:
As early as January 2026
Completion Date: no later than March 31, 2026

Plans

Specifications

SOW Kamoleao Landclearing_1 Acre Albezia Final w map.pdf

Addendums/Amendments