Bid Date: 2025-07-10

Project Description: The scope of work consists of the following: removal of seven (7) high mast light poles, luminaires, foundations, bollards, PCC pavement, and electrical system; the installation of one (1) new high mast light pole, foundation, bollards, and PCC pavement, and electrical system; the installation of new LED luminaires at all remaining light poles and the new light pole; the removal and relocation of one (1) fire hydrant, and the removal and replacement of the associated gate valve, valve box, piping, fittings, and concrete blocks. Remove and reinstall conductors from existing underground conduits. Trenching for new electrical conduits is required, along with patching the concrete and asphalt pavement. Coordination with Young Brothers and Hawaii District is required. Repair all concrete and AC pavement that is disturbed during construction.

Plans

Specifications

FINAL SPECIFICATIONS w NTB P50210.pdf

Addendums/Amendments
FINAL ADDENDUM NO 1 P50210 PLANS.pdf

FINAL ADDENDUM NO 1 P50210.pdf